Construction of a tunnel under the Dnieper in Kyiv: experts assess realistic timelines
The project to build a tunnel in the capital may take up to 7 years, despite optimistic government forecasts. Experts highlight the complexity of preparatory procedures.
Photo: UNIAN
Key points
- Tunnel construction could take up to 7 years.
- Tender procedures may take about a year.
- Project cost is estimated at 500 million dollars.
- Floating bridges are considered a quick alternative.
The issue of connectivity between the banks of the Dnieper in Kyiv has returned to the spotlight following plans to construct an underground tunnel. Despite initiatives to involve international partners, experts warn against drawing hasty conclusions regarding the timelines for such a large-scale infrastructure project.
Implementation complexity and timeframes
Oleksandr Davydenko, an associate professor at the Department of Bridges, Tunnels, and Hydraulic Structures at the National Transport University, emphasizes that even under the most favorable conditions, construction will take between 5 and 7 years. A significant portion of this time will be consumed not only by construction work but also by bureaucratic stages. Specifically, tender procedures alone could take about a year, excluding the time required for design documentation and logistics.
Meanwhile, the Minister for Restoration, Infrastructure, and Transport, Mykola Kalashnyk, previously stated that the minimum project timeline could be 2-3 years, with the cost of a basic tunnel estimated at 500 million dollars. It is currently known that the American company Robbins is ready to provide the necessary equipment and technical support for the project, which dates back to the 2004-2008 Kyiv General Plan.
Alternatives for transport connectivity
Experts are also considering less expensive and faster methods to improve logistics. These include the installation of floating bridges, which can be constructed in a matter of weeks, or the development of river transport. However, the latter option has limitations related to security challenges during air raids and general logistical feasibility.
Source UNIAN — unian.ua/economics/transport/tunel-pid-dniprom-u-kiyevi-ne-pobuduyu… ↗
Read next
Morocco Builds Giant Solar Power Plant That Generates Electricity at Night
The 580 MW Noor complex near the Sahara Desert uses thermal storage technology to continue producing electricity long after sunset.
🎭Culture & SportSignal restricts screenshots to protect user chats from AI agents
The secure messaging app Signal is implementing screenshot restrictions on iOS and Android to prevent data harvesting by operating system-integrated artificial intelligen…
Over 40,000 Roman-era coins discovered under a house in France
During home expansion work in northeastern France, researchers uncovered three caches containing more than 40,000 ancient Roman coins dating back about 1,700 years.
Western intelligence warns of Russian plans to deploy nuclear weapons in space this year
According to Western intelligence agencies, Russia is preparing to orbit a satellite equipped with a nuclear warhead, threatening global communications and navigation.
⚽SportUsyk swapped the ring for a basketball court in London and challenged NBA legend
Ukrainian boxer Oleksandr Usyk participated in a charity basketball match in the British capital, playing alongside legendary Scottie Pippen.
🩺HealthRussian Drone Attack Hits Lozova: Seven Injured as Fires Break Out in Residential Areas
A Russian strike drone attack targeted the city of Lozova in Kharkiv Oblast, injuring seven civilians. The impacts sparked fires in an apartment building and the private …